Every day, across Puerto Rico, our LUMA crews are performing “planned upgrade projects” on the electric grid to better serve you andyour family. Planned upgrade projects include a variety of important work to help improve the electric system you depend on. As we carry out this work, and to help ensure the safety of our LUMA field crews and the community, please know that planned upgrade projects can result in temporary service interruptions.

To help keep all our customers informed about when and where work is occurring and the progress of planned upgrade projects scheduled in your community, daily progress updates are available below

Planned Upgrade Project Details

Click here to view a map of active and planned projects.

 

Data as of 2024-11-21 09:23:14
Sheduled DateMunicipalityStreets Or Sectors ImpactedType of UpgradesEstimated Start TimeEstimated End Time
2024-11-21'BayamónN/AReplacing and Repairing Powerlines and Equipment08:00'19:00'
2024-11-21'PonceURB. PUNTO ORO, URB. EXT. PUNTO ORO I, URB. EXT. PUNTO ORO II, COMUNIDAD PUNTA DIAMANTEReplacing and Repairing Powerlines and Equipment09:00'17:00'
2024-11-21'Las PiedrasBo. Montones 3, Sector La Puesta del SolRemoving Hazardous Vegetation07:30'17:00'
2024-11-21'HormiguerosIGLESIA PRESNITERIANA VALLE HERMOSOS, IGLESIA DE CRSITO HORMIGUEROS, TIJERAS SALON, VALLE HERMOSO RETREAT, GENERAL REFRIGERATION CENTER, IGLESIA ADVENTISTA, PANADERIA Y REPOSTERIA KARY SHANGAI CHINA SUPERMERCADO NAPO VELEZ, ICE CREAM LAB & SHAKES, GR MOTORS SPORT Load Balancing8:30'18:00'
2024-11-21'CorozalPR-159 BO. ABRAS, BO. CIBUCO SECTORES RES. EL CENTRO, POLIDEPORTIVO COROZAL & PORTUGUES.Repairing or Replacing Poles06:00'18:00'
2024-11-21'Vega BajaCARR. 645 ALMIRANTE SURRepairing or Replacing Poles07:00'17:00'
2024-11-21'San JuanCALLE CONDADO 54 Y 59Replacing and Repairing Powerlines and Equipment09:30'10:30'
2024-11-21'PonceLIBERTY DE PONCE, CARIBE SHELVINGS WAREHOUSE PONCE, WOOD PALLET SOLUTIONS, CR QUALITY ROOFING PR. INC, EURO HOUSE, ANDUJAR CONSTRUCTION, PROCESS CONTROL SYSTEM SPECIALIST, TIENDITA HOLSUM, CORREA TIRE, ROD RODDER PONCE, OVEJA NEGRA, IGLESIA DE LA MERCED, EL ATERRIZAJE LA PARRILLLA, IGLESIA FARO DE LUZ, RAMON AUTO SERVICE AND TIRE, LA NUEVA PONCEÑA, POLLOS VAQUEROS. Removing Hazardous Vegetation08:00'16:00'
2024-11-21'PonceCALLE GIRASOL, CALLE DON DIEGO, CALLE ISABEL SEGUNDA, CALLE HIBISCUS, HELEN DE HARO FASHION DESIGN, CENTRO DE INSPECCION Y MARBETES SABANETAS, CARRIBEAN TRANSMISSIONSRemoving Hazardous Vegetation08:00'16:00'
2024-11-21'San JuanCALLE DEL CRISTO, FORTALEZA, LUNA, SOL. Repairing or Replacing Poles08:00'18:00'
2024-11-21'GuaynaboURB. TORRIMAR 2 CALLE MALAGARepairing or Replacing Poles10:00'18:00'
2024-11-21'CarolinaSUB. 1673-1 ICI PAINTSReplacing and Repairing Powerlines and Equipment 08:00'17:30'
2024-11-21'San JuanBO. CUPEY ALTO PR-176 KM 7.4 INT. CAMINO CUATRO CALLES.Repairing or Replacing Poles07:00'17:00'
2024-11-22'CaguasANTENA T MOBILE AVE. BAIROA CAGUAS.Underground Maintenance and Repair07:00'15:30'
2024-11-22'CorozalPR-807 BO. DOS BOCAS I.Repairing or Replacing Poles06:00'18:00'
2024-11-22'MaunaboZONA URBANA, QUEBRADA ARENAReplacing and Repairing Powerlines and Equipment09:00'15:30'
2024-11-22'GuaynaboCALLE PIEDRAS BLANCA GUAYNABO.Repairing or Replacing Poles09:00'17:00'
2024-11-22'PonceURB. PUNTO ORO, MONTEMAR APARTMETSReplacing and Repairing Powerlines and Equipment09:00'17:30'
2024-11-22'CoamoBO SANTA CATALINA COAMO CARR #150Distribution Feeder Maintenance / Repair (Mantenimiento/Reparación Alimentadores Distribución) y Desganche (Vegetación)09:00'16:00'
2024-11-22'CarolinaURB. CIUDAD JARDIN CALLE ORQUIDIS, TRINITARIA, AMAPOLA, LIRIO, AZUCENA, LILA, GARDENIA, VIOLETA, HORTENCIA Y GLADIOLA
LOS COLOBOS I, PETSMART
Repairing or Replacing Poles07:30'18:30'
2024-11-22'CarolinaCONDOMINIO ANDALUCIA, CHALÉS DE SAN FERNANDO, CONDOMINIO PARQUE JULIANA, URB. CIUDAD JARDIN CALLE ORQUIDIS, TRINITARIA, AMAPOLA, LIRIO, AZUCENA, LILA, GARDENIA, VIOLETA, HORTENCIA Y GLADIOLA
CORECIOS EN LOS COLOBOS I, PETSMART, CAMINO MONOLORO
Repairing or Replacing Poles07:30'18:30'
2024-11-22'CaguasANTENA T MOBILE AVE. BAIROA CAGUAS.Underground Maintenance and Repair07:00'15:30'
2024-11-23'CarolinaSUB 1674 ECONOReplacing and Repairing Powerlines and Equipment 07:00'17:00'
2024-11-23'San JuanLAS LOMAS, COND. CIUDAD LUMEN, IGLESIA PRIMERA FUENTE DE SALVACION, AVE SAN IGNACIO, COND SAN IGNACIO, COND LA PROVIDENCIA, COND. VISTA VERDE, VILLAS DE SAN FRANCISCO, VILLAS DE SAN IGNACIO, RES. SAN FERNANDORemoving Hazardous Vegetation07:00'07:30'
2024-11-23'CarolinaSUB 1674 ECONONReplacing and Repairing Powerlines and Equipment 07:00'17:00'
2024-11-23'San JuanBO. CUPEY ALTO PR-176 KM 7.4 INT. CAMINO CUATRO CALLES.Repairing or Replacing Poles07:00'17:00'
2024-11-23'San JuanSUPERITENDENCIA CAPITOLIO, MUSEO GUARDIA NACIONAL Y ESCUELA JOSE CELSO BARBOSAReplacing and Repairing Powerlines and Equipment09:30'16:00'
2024-11-23'San JuanSUPERITENDENCIA CAPITOLIO, MUSEO GUARDIA NACIONAL Y ESCUELA JOSE CELSO BARBOSAReplacing and Repairing Powerlines and Equipment09:30'16:00'
2024-11-23'CorozalPR-821 BO. ABRAS.Repairing or Replacing Poles06:00'18:00'
2024-11-23'San JuanLAS LOMAS, COND. CIUDAD LUMEN, IGLESIA PRIMERA FUENTE DE SALVACION, AVE SAN IGNACIO, COND SAN IGNACIO, COND LA PROVIDENCIA, COND. VISTA VERDE, VILLAS DE SAN FRANCISCO, VILLAS DE SAN IGNACIO RES. SAN FERNANDORemoving Hazardous Vegetation17:30'18:00'
2024-11-23'San JuanLAS LOMAS, COND. CIUDAD LUMEN, IGLESIA PRIMERA FUENTE DE SALVACION, AVE SAN IGNACIO, COND SAN IGNACIO, COND LA PROVIDENCIA, COND. VISTA VERDERemoving Hazardous Vegetation07:30'17:30'
2024-11-25'MocaBO. ROCHA MOCAReplacing and Repairing Powerlines and Equipment08:00'17:00'
2024-11-25'BayamónURB. SANTA JUANITA CALLE RENO & AVE. SANTA JUANITA.Removing Hazardous Vegetation08:00'16:00'
2024-11-25'Vega altaSUB. 9176 PANAMERICAN PROPERTIES, SUB. 9171 MR. SPECIAL, SUB. 9170 INDUSTRIAL C & S OF PR.Replacing and Repairing Powerlines and Equipment 08:00'16:30'
2024-11-25'San JuanCALLES FORTALEZA, Y TETUAN VIEJO SAN JUAN. Repairing or Replacing Poles08:00'19:00'
2024-11-25'Vega BajaBO. ALMIRANTE SECTOR LOS MARRERORepairing or Replacing Poles07:00'17:00'
2024-11-26'AreciboSUB. 8089 UNIVERSIDAD INTERAMERICANA DE ARECIBOReplacing and Repairing Powerlines and Equipment 08:00'19:00'
2024-11-26'PonceURB. PUNTO ORO, URB. EXT. PUNTO ORO I, URB. EXT. PUNTO ORO II, COMUNIDAD PUNTA DIAMANTEReplacing and Repairing Powerlines and Equipment
2024-11-26'AreciboSUB. 8089 UNIVERSIDAD INTERAMERICANA DE ARECIBOReplacing and Repairing Powerlines and Equipment 08:00'19:00'
2024-11-26'CoamoURB LAS AGUILAS CALLES 4, 6, 7, 8Replacing and Repairing Powerlines and Equipment09:00'15:30'
2024-11-26'CorozalBARRIO PALOS BLANCOSRepairing or Replacing Poles07:00'17:00'
2024-11-26'AibonitoBARRIO ASOMANTE SECTOR LAS ABEJAS, URBANIZACION RANCHETESRepairing or Replacing Poles08:30'15:30'
2024-11-26'LajasBO. PIEDRAS BLANCAS CALLE VILLA ANITA INTERIOR.Removing Hazardous Vegetation08:00'15:30'
2024-11-26'CarolinaCAMINO LOS MARQUEZ, PARQUE JULIANA, CALLE ANTULIOS, CALLE MARGARITA, ESTANCIAS DEL PARQUE, CALLE CORAZON, CALLE HAEIEDITA, CALLE MONOLORO, CALLE ALMENDRO Y PORTICOS DEL SOL.Repairing or Replacing Poles07:30'18:30'
2024-11-26'Las PiedrasMontones 3Removing Hazardous Vegetation07:30'17:00'
2024-11-27'CaguasSUB 3060-1 & SUB 3060-2 DEL HOSPITAL HIMAReplacing and Repairing Powerlines and Equipment 07:00'17:00'
2024-11-27'GuayamaBO. PALMAS BAJAS & PALMAS ALTAS.Replacing and Repairing Powerlines and Equipment09:00'15:30'
2024-11-27'CaguasSUB 3060-1 & SUB 3060-2 DEL HOSPITAL HIMAReplacing and Repairing Powerlines and Equipment 07:00'17:00'
2024-11-27'Las PiedrasBo. Montones 2, El RomiarRemoving Hazardous Vegetation07:30'17:00'
2024-11-27'BayamónURB.SANTA MONICA CALLE 2 BAYAMONRemoving Hazardous Vegetation07:00'18:00'
2024-11-27'BayamónReparto Teresita,El Volcan,Park West,Bayamón Oeste Shopping,Zona Industrial Corujo(parcial),NUC University,Carr.864 Hato Tejas,Egida Los Cantares,Hospital Juan Alamo Diaz, JF Montalvo.Replacing and Repairing Powerlines and Equipment06:00'18:00'
2024-11-27'JuncosURBANIZACION REPARTO VALENCIANOInstalling Grid Automation Devices08:30'14:30'
2024-11-27'JuncosURBANIZACION REPARTO VALENCIANOInstalling Grid Automation Devices08:30'14:30'
2024-11-28'GuayamaBO. LAS MAREAS DE GUAYAMA CARR. # 3 INT. # 710Distribution Feeder Maintenance / Repair (Mantenimiento/Reparación A5limentadores Distribución)09:00'15:30'
2024-11-28'CaguasTURABO GAREN , BONEBILLE, ESTANCIAS DEGETAU, VILLA HERMOSARemoving Hazardous Vegetation07:00'16:00'
2024-11-29'BayamónURB. SANTA JUANITA CALLE INDIA.Removing Hazardous Vegetation08:00'18:00'
2024-11-29'GuayamaBO. BARRANCA CARR. #3 INT. CARR. 710Replacing and Repairing Powerlines and Equipment09:00'15:30'
2024-11-29'GuaynaboCALLE PIEDRAS BLANCA GUAYNABO.Repairing or Replacing Poles09:00'17:00'
2024-12-03'PonceCOMPLEJO DE APARTAMENTOS, GOLDEN VIEW Y SILVER VALLEY Underground Maintenance and Repair08:00'16:00'
2024-12-03'Toa AltaCONTORNO,RABO DEL BUEY,EL WINCHE,QUEBRADA ARENAS,BO.GALATEO,EL JOSCO,VEREDAS DEL RIO,HACIENDA LYDIA MARIE.Removing Hazardous Vegetation07:00'17:00'
2024-12-04'HumacaoMARBELLA CLUB, PALMAS DEL MARUnderground Maintenance and Repair09:00'14:30'
2024-12-04'San SebastiánCARREERA 119 BARRIO HOYAMALA Y BARRIO AIBONITO GUERREROReplacing and Repairing Powerlines and Equipment07:00'19:00'
2024-12-04'Toa AltaCOLINAS DEL PLATA,VEREDAS DE LA REINA,CAMPOS DEL TOA,TRRES DEL PLATA,ALTURAS DE BUCARABONES, LOS RODRIGUEZ.Removing Hazardous Vegetation07:00'17:00'
2024-12-04'IsabelaCar 113 Bo. Guayabo, Bo. Cotto y Car 474 Bo. Galateo, IsabelaFeeder Relocation (Relocalizacion de Alimenatdor)07:00'20:00'
2024-12-04'Toa AltaLA PRARemoving Hazardous Vegetation07:00'17:00'
2024-12-04'Toa AltaCOLINAS DEL PLATA,VEREDAS DE LA REINA,CAMPOS DEL TOA,TRRES DEL PLATA,ALTURAS DE BUCARABONES, LOS RODRIGUEZ.Removing Hazardous Vegetation07:00'17:00'
2024-12-04'AreciboSUB. 8097 Super AcueductoReplacing and Repairing Powerlines and Equipment 08:00'17:00'
2024-12-04'HumacaoMARBELLA CLUB PALMAS DEL MAR, HUMACAOUnderground Maintenance and Repair09:00'14:30'
2024-12-05'Trujillo AltoCAMINO LOS APONTE, CAMINO EL MUDO, CAMINO PEPE MORALES, CALLE1Repairing or Replacing Poles6:00'18:00'
2024-12-05'Trujillo AltoCAMINO LOS APONTE, CAMINO EL MUDO, CAMINO PEPE MORALES, CALLE1Repairing or Replacing Poles6:00'18:00'
2024-12-06'GuaynaboCALLE PIEDRAS BLANCA GUAYNABO.Repairing or Replacing Poles09:00'17:00'
2024-12-08'PonceFURIER AUTO, PARQUE MONAGAS, GIL FARMACEUTICAL, BELLA GROUP,
As Customer Request08:00'12:00'
2024-12-08'PonceCASAS MI ESTILO, LEXUS, CASA DE OS TORNILLOS, SEÑORIAL AUTOMOTIVE, SEGUROS MULTIPLES, INFINITY, MOTOR AMBAR, REFRICENTRO, CLINICA PININOS, ISLAND CREAMERY, FORD DEL SUR OUTLET, WENDYS, KFC, MCDONALDS, GARAGE ESSO, SUBWAY, FEDEX, HUNDAY DE PONCE, CHURCH, BASKING ROBINSAs Customer Request08:00'
2024-12-09'San juanSECT. LA CERÁMICA
Restoring and Rebuilding Substations06:00'23:00'
2024-12-10'IsabelaCARRETERA 446 PASEO LOS FIGUEROA BO LLANADA ISABELA.Load Balancing09:30'12:00'
2024-12-10'San Juan529 Calle Fernando Calder, San Juan, 00918 & 522 Calle Ing Alfredo Carbonell, San Juan, 00918Removing Hazardous Vegetation07:00'17:00'
2024-12-10'San Juan529 Calle Fernando Calder, San Juan, 00918 & 522 Calle Ing Alfredo Carbonell, San Juan, 00918Removing Hazardous Vegetation07:00'17:00'
2024-12-11'GuayamaNUC UNIVERSITY , SECT. PASEO DEL PUEBLOReplacing and Repairing Powerlines and Equipment10:00'14:30'
2024-12-11'GuayamaCOMPLEJO DEPORTIVO MUNICIPAL DE GUAYAMA, CMPG. OBRAS PÚBLICAS, COMU. CIMARRONA, COND. ÉGIDA BRISAS DEL MAR ELDERLY, CENTRO DE CONVENCIONES DE GUAYAMA, RESIDENCIAL VALLES DE GUAYAMA, SECT. CASCO URBANO, SECT. PASEO DEL PUEBLO, URB. BRISAS DEL MAR, URB. CAMINO DE LA PRINCESA,Replacing and Repairing Powerlines and Equipment09:00'10:00'
2024-12-11'CidraBDA. FERRER, COMU. FÁTIMA, COMU. LAS FLORES, EDU. ESCUELA CLEMENCIA MELÉNDEZ, PARC. LA MILAGROSA, RES. RESIDENCIAL JARDINES DE CIDRA, SECT. ALMIRANTE, SECT. ALTURAS DE CIDRA, SECT. BERRÍOS, SECT. CAPILLA, SECT. CASCO URBANO, SECT. CASTRODAD, SECT. CHICHÓN, SECT. COTTO, SECT. FEDERICO RAMOS, SECT. GALINDO, SECT. HACIENDAS DE CIDRA, SECT. JARDINES DE RABANAL, SECT. LA LOMA, SECT. LOS NIEVES, SECT. LOS PANES, SECT. MELÉNDEZ, SECT. PALMA SOLA, SECT. RIVERA, SECT. RODRÍGUEZ, SECT. TIERRA LINDA, URB. DOMINGO RODRÍGUEZ, URB. VILLAS DE SAN IGNACIORestoring and Rebuilding Substations6:00'08:00'
2024-12-11'GuayamaCOMPLEJO DEPORTIVO MUNICIPAL DE GUAYAMA, CMPG. OBRAS PÚBLICAS, COMU. CIMARRONA, COND. ÉGIDA BRISAS DEL MAR ELDERLY, CENTRO DE CONVENCIONES DE GUAYAMA, RESIDENCIAL VALLES DE GUAYAMA, SECT. CASCO URBANO, SECT. PASEO DEL PUEBLO, URB. BRISAS DEL MAR, URB. CAMINO DE LA PRINCESA, Replacing and Repairing Powerlines and Equipment14:30'15:30'
2024-12-12'AibonitoURB CAMPO REY, URB VILLA ROSALESRestoring and Rebuilding Substations06:30'20:00'
2024-12-12'AibonitoCOME. PLAZA LAS FLORES SHOPPING CENTER, PARC. RABANAL, RES. RESIDENCIAL LAS FLORES, SECT. AMOLDADEROS, SECT. LA BASE, SECT. LA CALLE, SECT. LA FRATERNIDAD, SECT. LA SIERRA, SECT. LOS MUROS, SECT. RABANAL, URB. BELLA VISTA, URB. BRISAS DE AIBONITO, URB. EXTENSIÓN BELLA VISTA, URB. EXTENSIÓN SAN JOSÉ, URB. LAS MERCEDES, URB. LAS QUINTAS, URB. PASEO MONTE CARLO, URB. REPARTO ROBLES, URB. SAN JOSÉ, URB. VALLE DE LA PLATA, URB. VILLA VERDERestoring and Rebuilding Substations06:30'20:00'
2024-12-12'AguadillaBO MORA SECTOR CAJIGAS ISABELA ENTRANDO POR FUNERARIA EL NOROESTELoad Balancing09:30'12:00'
2024-12-12'AibonitoBO PUEBLO,Restoring and Rebuilding Substations06:30'20:00'
2024-12-17'IsabelaBO LLANADAS, CALLE CASIMIRA RAMOS CARRETERA 446 INTERIOR Load Balancing09:30'12:00'
2024-12-17'IsabelaBO LLANADAS, CALLE CASIMIRA RAMOS CARRETERA 446 INTERIOR Load Balancing09:30'12:00'
2024-12-19'IsabelaCAR 475 BO. LLANADAS SEC. CALICHOSA Y MONTADEROLoad Balancing09:00'12:00'
2024-12-19'IsabelaCAR 475 BO. LLANADAS SEC. CALICHOSA Y MONTADEROLoad Balancing09:00'12:00'

Legend

TYPES OF UPGRADES

  • Installing Grid Automation Devices that remotely detect outages and reduce the number customers impacted
  • Replacing and Repairing Powerlines and Equipment connected to substations or along major roadways to improve reliability
  • Increasing Utility Pole Resiliency by replacing old or broken wooden poles with stronger galvanized steel utility poles
  • Restoring and Rebuilding Every Substation across Puerto Rico as part of LUMA’s Substation Modernization Initiative
  • Installing Thousands of Modern Streetlights and providing greater visibility and security to communities as part of LUMA’s Community Streetlight Initiative
  • Removing Hazardous Vegetation from powerlines to increase reliability and allow for modernization upgrades on critical infrastructure across the island