Keeping You Informed About Our Planned Upgrade Projects
Every day, across Puerto Rico, our LUMA crews are performing “planned upgrade projects” on the electric grid to better serve you andyour family. Planned upgrade projects include a variety of important work to help improve the electric system you depend on. As we carry out this work, and to help ensure the safety of our LUMA field crews and the community, please know that planned upgrade projects can result in temporary service interruptions.
To help keep all our customers informed about when and where work is occurring and the progress of planned upgrade projects scheduled in your community, daily progress updates are available below
Sheduled Date | Municipality | Streets Or Sectors Impacted | Type of Upgrades | Estimated Start Time | Estimated End Time |
---|---|---|---|---|---|
2024-04-27' | San Juan | AVE.65TH INFANTERIA. | Repairing or Replacing Poles | 7:00' | 19:00' |
2024-04-27' | San Juan | PARCELAS FALU. | Repairing or Replacing Poles | 7:00' | 19:00' |
2024-04-27' | San Juan | Calles 10, 31,3 LOS PEÑA EN AVE.65TH NFANTERIA, ESQ. SIMON MADERA, RIO PIEDRAS | Repairing or Replacing Poles | 7:00' | 19:00' |
2024-04-27' | San Juan | PARCELAS FALU. | Repairing or Replacing Poles | 7:00' | 19:00' |
2024-04-28' | Arecibo | SUB. 8073 EATON, SUB. 8093 CUTLER HAMMER, SUB. 8099 CUTLER HAMMER AND 8069 CUTLER HAMMER | Repairing or Replacing Poles | 07:00' | 18:00' |
2024-04-28' | San Juan | Escuela Dr. Facundo Bueso | Repairing or Replacing Poles | 7:00' | 17:00' |
2024-04-29' | Las marias | CARR. 119 BO. MARAVILLA NORTE, BO. ESTE SECTOR CAMINO DE LA VEGA DEL COMBATE Y LA CALZADA. | Repairing or Replacing Poles | 7:00' | 16:00' |
2024-04-29' | Bayamón | AVE. RAMON E. BETANCES, BO. HATO TEJAS | Repairing or Replacing Poles | 9:30' | 18:00' |
2024-04-29' | Humacao | PR-925 KM 0.9 INT. BO. PASTO VIEJO & RIO ABAJO. | Repairing or Replacing Poles | 7:00' | 18:00' |
2024-04-29' | San Germán | CARR. 119 & CARR. 348 BO. HONOCONUCO | Repairing or Replacing Poles | 7:30' | 17:30' |
2024-04-30' | Humacao | SECT. CASCO URBANO, URB. EXTENSIÓN PATAGONIA, URB. LOS PINOS, URB. LOS PINOS ROW HOUSES, URB. VILLA PATAGONIA | Restoring and Rebuilding Substations | 9:00' | 10:00' |
2024-04-30' | Humacao | SECT. CASCO URBANO, URB. EXTENSIÓN PATAGONIA, URB. LOS PINOS, URB. LOS PINOS ROW HOUSES, URB. VILLA PATAGONIA | Restoring and Rebuilding Substations | 9:00' | 10:00' |
2024-04-30' | San Sebastián | BO. SALTO | Repairing or Replacing Poles | 8:00' | 19:00' |
2024-04-30' | Vega Baja | URB. LA HACIENDA LA ARBOLEDA, URB. LAS DELICIAS, URB. MONTE CARLO, URB. QUINTAS DE TORTUGUERO, URB. VEGA BAJA LAKES, URB. VILLA CURIEL, COMU. CANTERA, URB. CAMINO DEL SOL 2, COME. LAS VEGAS SHOPPING CENTER, COMU. BRISAS DE TORTUGUERO, COMU. OJO DE AGUA, COND. CHALETS DE LA PAYA, COND. PISOS REALES, COND. VEREDAS DEL MAR, IGL. IGLESIA DE DIOS MISSION BOARD, IGL. PRIMERA IGLESIA BAUTISTA DE VB , SECT. CRIOLLO, SECT. GUÁRICO, SECT. GUÁRICO VIEJO, SECT. HACIENDA BAUDILLO, SECT. REPARTO LA PROVIDENCIA, URB. CAMINO DEL SOL, URB. CIUDAD REAL, URB. ESTANCIAS DE TORTUGUERO, URB. ESTANCIAS DE TORTUGUERO 2, URB. EXTENSIÓN GUÁRICO, URB. GUÁRICO, URB. HACIENDA DE TORTUGUERO, URB. JARDINES DE VEGA BAJA, COMU. LOS PUERTOS, SECT. MARISMILLA, SECT. VILLA PALMAS, URB. JARDÍN DORADO, URB. LOS PRADOS DE DORADO NORTE, URB. LOS PRADOS DE DORADO SUR, COME. PLAZA DEL MAR SHOPPING CENTER, COMU. BREÑAS, COMU. CARMELITA, COMU. CERRO GORDO, COMU. VILLA ALEGRÍA, COMU. VILLA RETORNO, COND. EL DORADO CLUB, COND. GOLD VILLAS, COND. LAKESIDE VILLAS, COND. LOMAS DEL MAR, COND. NORTH COAST VILLEGE, COND. PALMA DORADA VILLAGE, COND. ROYAL PALM, SECT. BREÑAS, SECT. HACIENDAS DEL MAR, SECT. SABANA HOYOS, SECT. SABANA HOYOS SANTANA, URB. ALTURAS DE CERRO GORDO 3, URB. CAPITÁN DEL MAR, URB. CERRO GORDO HILLS, URB. CIELO DORADO VILLAGE, URB. COCONUT COURT, URB. ESTANCIAS DE CERRO GORDO, URB. ESTANCIAS DE SAN NICOLÁS, URB. EVERGREEN 2, URB. GOLDEN VILLAGE, URB. GRAND PALM, URB. GRAND PALM 2, URB. HACIENDAS DEL MOLINO, URB. LAS PALMAS DE CERRO GORDO, URB. OCEAN BREEZE, URB. PALMAS DE CERRO GORDO, URB. PERLA DEL SUR, URB. TREASURE POINT, URB. VEGA DORADA, U, URB. EL VERDE, URB. EXTENSIÓN BETANCES | Restoring and Rebuilding Substations | 6:00' | 19:30' |
2024-05-02' | Arecibo | 1 | Feeder Relocation (Relocalizacion de Alimenatdor) | false' | |
2024-05-03' | Adjuntas | 1 | Installing Grid Automation Devices | false' | |
2024-05-03' | Adjuntas | 1 | Installing Grid Automation Devices | false' | |
2024-05-03' | Añasco | 2 | Feeder Relocation (Relocalizacion de Alimenatdor) | 08:00' | 11:00' |
2024-05-04' | Añasco | 2 | Installing Grid Automation Devices | 09:15' | 09:30' |
2024-05-04' | Añasco | 2 | Installing Grid Automation Devices | 09:15' | 09:30' |
2024-05-04' | Adjuntas | 3 | Feeder Relocation (Relocalizacion de Alimenatdor) | 11:00' | |
2024-05-05' | Arecibo | 3 | Installing Grid Automation Devices | 11:15' | |
2024-05-05' | Arecibo | 3 | Installing Grid Automation Devices | 11:15' | |
2024-05-05' | Aguadilla | 4 | Feeder Relocation (Relocalizacion de Alimenatdor) | 08:00' | 11:00' |
2024-05-06' | Adjuntas | 4 | Installing Grid Automation Devices | 10:45' | 11:45' |
2024-05-06' | Adjuntas | 4 | Installing Grid Automation Devices | 10:45' | 11:45' |
2024-05-06' | Aibonito | 5 | Feeder Relocation (Relocalizacion de Alimenatdor) | 08:00' | 11:00' |
2024-05-07' | Arecibo | 5 | Installing Grid Automation Devices | 09:30' | 10:45' |
2024-05-07' | Arecibo | 5 | Installing Grid Automation Devices | 09:30' | 10:45' |
Legend
TYPES OF UPGRADES