If you are interested in connecting your renewable energy sources, please follow these steps.
1. INFORMATION
Customer can research Net Metering Information at LUMA, by clicking here.
- Review and Understand the Regulations
- Revew the Application Manual
- Access to all Required Forms
Responsibility: Customer
2. APPLICATION
Customer Applies to LUMA for Net Metering through the DG Portal by clicking here.
- Create an account on the Distributed Generation Portal
- Use your LUMA Service Account ID to create the account
- Attach all completed forms with your application through the portal
Responsibility: Customer
3. LUMA APPLICATION REVIEW
LUMA will review application to ensure the required documents and information are included
- LUMA will contact the client through the portal if any information is missing, unclear or incorrect.
Responsibility: LUMA
4. LUMA TECHNICAL VALIDATION
LUMA will complete a technical validation of the application
- Field assessments may be required based on the size of the Distributed Generation Connection
- If a supplementary study is needed, payment of the study is done by customer through portal.
- If the case is above 25 kW or Transmission connected, additional activities or documentation may be required.
Responsibility: LUMA
5. DG CONNECTION APPROVAL
- LUMA will contact the client through the DG portal to advise the connection is approved within 30 days of customer application
Responsibility: LUMA
6. SIGN NET METERING AGREEMENTS AND INSURANCE
- Customer must sign the net metering agreement on the Distributed Generation portal
- Customer must obtain Public Liability Insurance for Distributed Generation capacity greater than 300kW
Responsibility: Customer
4. LUMA TECHNICAL VALIDATION
LUMA will complete a technical validation of the application
- Field assessments may be required based on the size of the Distributed Generation Connection
- If a supplementary study is needed, payment of the study is done by customer through portal.
- If the case is above 25 kW or Transmission connected, additional activities or documentation may be required.
Responsibility: LUMA
5. DG CONNECTION APPROVAL
- LUMA will contact the client through the DG portal to advise the connection is approved within 30 days of customer application
Responsibility: LUMA
6. SIGN NET METERING AGREEMENTS AND INSURANCE
- Customer must sign the net metering agreement on the Distributed Generation portal
- Customer must obtain Public Liability Insurance for Distributed Generation capacity greater than 300kW
Responsibility: Customer
7. BI-DIRECTIONAL METER INSTALLATION
Once the request has passed technical validation, the site must have a bi-directional meter to accurately measure the energy the customer is producing.
- Some meters already have bi-directional measurement capabilities already
- If a bi-directional meter is not already installed, LUMA will send a technician to change the meter
Responsibility: LUMA
8. TARIFF CHANGE
- Once a bi-directional meter is installed, LUMA Billing Services team will update the Service Agreement to include a tariff change that will be represented on the following month’s invoice to the customer.
- A Service agreement will be issued from the portal.
Responsibility: LUMA
9. ANNUAL NET METER CREDIT
- If a cutomer site produces more energy than it requires, a credit will be applied to the service agreement once per year in June for the previous 12 months.
Responsibility: LUMA